Starting last Monday, the centre of the pitch has been completely replaced.
Work began to excavate a square covering the centre of the pitch, to a depth of 200mm, before the area was filled with sand.
Fresh turf was installed on top of the new material, followed by the area being restitched – the insertion of synthetic fibres – over the weekend.
On Wednesday, the pitch will be Dryjected, a process which assists in allowing any retained water the best possible chance of draining through.
A timeline of pictures can be found below, which details each stage of the work undertaken.